Design
Approach:
Thermo Bond Buildings are designed, built, and wired to
protect critical electronic equipment from the environment.
We do nothing else.
We make nothing else.
There is no substitute for the hands-on, practical
experience we’ve gained over the past 3 decades by working
closely with people like you.
We understand the problems you face.
It is our responsibility to do so, and we take this
responsibility very seriously.
|
|
Size
and Specifications: The shelter will be constructed to meet your needs, with sizes
ranging from 4’ x 6’ up to 24+’ width by 42’ length.
The specs that follow describe a “standard” Thermo
Bond building, however many custom options in materials and
design are available. Consult
a Thermo Bond sales representative to learn how we can help
solve your problems.
|
|
Floor
Loading: The minimum
floor loading will be 200 pounds per square foot. |
|
Roof
Loading:
The minimum roof loading will be 100 pounds per square foot. |
|
Roof
Impact Resistance: The
minimum roof impact resistance will be 220 foot-pounds with no
damage to either the exterior or interior of the roof or
shelter. |
|
Wall
Wind Load:
The minimum wall wind load is 120 mph. |
|
Air
Infiltration: There
will be no air infiltration of the shelter when measured
before installation of any through-the-wall, floor or roof
items when exposed to winds of 50 mph. |
|
Skid
Assembly: The skid assembly for the shelter will have a minimum of two
6" x 9 lb. beams and welded into place. 2" x 2"
x ¼” angles will be place between the beams every 4' O.C.
The complete skid assembly will be painted with rust resistant
paint or hot dipped galvanized after fabrication.
|
|
Floor
Assembly: The floor
system will be comprised of one layer of 3/4" CDX plywood
(exterior) and 1 layer of 3/4" tongue and groove plywood
(interior) attached to joists, 16” O.C.
Before the floor is assembled and the rodent shield
installed, a penetrating liquid bituminous sealer will be
applied. The
interior core of the floor will be filled with R-11 fiberglass
batt insulation. |
|
Rodent
Shield:
The complete underside of the floor assembly will be covered
with a 16-mesh .011 wire mesh rodent shield before the floor
assembly is attached to the skid assembly.
|
|
Interior
Floor Finish: The
interior surface of the shelter floor will be covered with a
commercial grade vinyl tile. |
|
Exterior
Wall Finish:
The standard exterior finish is the Thermo Bond Aggregate
Panel. The panel
is widely used in the construction of office buildings and
commercial property and requires minimal maintenance.
|
|
Wall
Construction: The
interior walls will be a minimum of 5/8" OSB (oriented
strand board) with .030 fiberglass reinforced plastic
laminated to the interior side.
The interior cores of the wall system will be filled
with R-11 fiberglass batt insulation. |
|
Roof
system: The roof system will be comprised of 1 layer of 3/4" CDX
plywood (exterior) and 1 layer of a minimum 5/8” OSB
(oriented strand board) with .030 fiberglass reinforced
plastic laminated to the interior side.
The interior cores of the roof system will be filled
with R-19 fiberglass batt insulation.
|
|
Seams:
At all points in the structure where two pieces of material
come together, butt against each other, overlap each other or
are fastened one to the other, the seams will be sealed with
industrial grade adhesive sealer during and after final
assembly to insure water tight joints. |